We have had a productive week on the tarmac surfacing works to the southern roundabout and have completed the base layer to two of the roads leading up to the new roundabout. However, due to the weather forecast for this week, the remainder of the works are taking place between the 23rd February and the 6th March. Night closures will be implemented during this period.

We thank you in advance for your patience and understanding during this period and we will be taking steps to ensure that any disturbance is kept to a minimum.